1
Removing the Blower from
the Crate
Parts needed for this procedure:
2
Caster
4
Bolt
4
Flange locknut
Procedure
Important:
Ensure that the jack stand is installed
to stabilize the blower before you unbolt the
blower frame from the shipping crate or remove
the crate.
1.
Remove the top of the crate
1. Top of crate
2. End of crate
2.
Remove the end of the crate which is toward the
top of the machine
3.
Remove the board that is under the blower
housing
(Figure
3).
4.
Remove the caster wheels from the crate.
5.
Install the caster wheels to the machine with 4
bolts (1/2 x 3-1/2 inch) and 4 flange locknuts
(1/2 inch); refer to
(Figure
3).
Figure 3
3. Top of machine
4. Board under blower
housing
(Figure
3).
Figure
4.
1.
Bolt (1/2 x 3-1/2 inch)
2. Caster wheel
6.
Secure a strap to the top end assembly and lift
the pallet until the crate and blower is standing
up vertically
g362308
1. Lift strap
7.
Remove the snapper pin securing the jack-stand
tube to the storage tube
jack assembly from the storage position.
6
Figure 4
3. Flange locknut (1/2 inch)
(Figure
5).
Figure 5
2. Top end assembly
(Figure
6). Remove the
g362310
g027060