Clearance Requirements - Cisco 8100 Series Hardware Installation

Table of Contents

Advertisement

Prepare for Installation
Step 1
Place the rack at the location where you plan to install the chassis.
Step 2
(Optional) Secure the rack to the floor.
To bolt the rack to the floor, a floor bolt kit (also called an anchor embedment kit) is required. For information on bolting
the rack to the floor, consult a company that specializes in floor mounting kits (such as Hilti; see
Make sure that floor mounting bolts are accessible, especially if annual retorquing of bolts is required.
Ensure that the rack in which the chassis is being installed is grounded to earth ground.
Note

Clearance Requirements

The chassis requires front-to-back airflow. Leave at least 6.0 in. (15.24 cm) front and rear clearance for air
intake or exhaust. We recommend that you have at least 6.0 in. (15.24 cm) of space in front of the chassis to
provide room to maneuver the cables to make the required connections. Leave an extra 6.0 in. (15.24 cm) rear
clearance for removal and installation of power supplies and fan modules.
Figure 9: Clearances Required Around the Chassis for Cisco 8102-64H
1
2
Chassis
4
6.0 in. (15.24 cm) front
5
clearance for air
intake/exhaust.
Hardware Installation Guide for Cisco 8100 Series Routers
Clearance Requirements
Hilti.com
for details).
6.0 in. (15.24 cm) rear
clearance for air
intake/exhaust.
More 6.0 in. (15.24 cm)
rear clearance for removal
and installation of power
supplies and fan modules.