Removing the shipping bracket and connecting power cords and
power distribution unit (PDU) for your preinstalled server
You must remove the shipping bracket and cable ties before cabling the server.
To remove the shipping bracket and cable ties, complete the following steps:
1. Using wire cutters, clip and remove the orange plastic ties that secure the power supplies to the
shipping bracket.
2. Remove the four screws that secure the shipping bracket to the chassis. Store the shipping bracket if
you want to move your system at a later date.
3. Gently push the power supplies into the system chassis until they lock into place.
4. Cable the server.
a. Plug the power cords into the power supplies (A). See Figure 21.
b. Route the power cords and other cables on the cable-management arm.
c. Secure the cord and cables with cable ties or hook-and-loop fasteners (B), as shown in Figure 21.
Figure 21. Plugging in the power cords and securing the cables with fasteners
d. If you have a disk drive enclosure or expansion drawer that came preinstalled in this rack, use the
documentation supplied with these options. For information about connecting enclosures and
expansion units, see Enclosures and expansion units (http://www.ibm.com/support/
knowledgecenter/POWER8/p8ham/p8ham_kickoff.htm).
e. Attach the PDU input power cord and plug it into the power source.
Note: If you are using redundant PDUs, verify that each of the power supplies are cabled and
configured for redundancy.
5. If you ordered a fully-populated system, there are additional tasks you must perform so that you can
access the line cord. To access the line cord on a fully-populated system, perform the following tasks:
28
Power Systems: Installing the IBM Power System E850 (8408-E8E)

Advertisement

Table of Contents
loading

This manual is also suitable for:

8408-e8e

Table of Contents