16. Roller Opener Installation
1. With the liftgate in the stored position, lower the
platform and position the opener on the step so it
contacts the tip of the ramp half of the platform
(Figure 46).
2. If the liftgate operates properly, weld the roller opener
into position (Figure 47). Repeat these steps for the
other side.
XL-TG10149IM-en-US Rev A 12-10 Amendments and Errors Reserved. © SAF-HOLLAND, Inc.
Roller Opener Installation
Figure 46
Figure 47
STEP WELDMENT
ROLLER OPENER
RAMP HALF OF
THE PLATFORM
APPROXIMATE LOCATION
TYP BOTH
SIDES
1/4"
STEPS
ROLLER OPENER