INSTALLATION

TO REMOVE EXISTING TOILET
Turn off the water supply. Flush the toilet, and use a
sponge to remove the remaining water from the tank
and bowl. Disconnect the supply shut-off valve (if
present), and remove the old tank and bowl.
Remove the old wax gasket from the closet flange with
a putty knife. Remove the old T-bolts and discard them.
NOTICE: If the new toilet is not installed immediately,
temporarily stuff a rag into the closet flange.
Install two new 5/16" diameter T-bolts into the closet
flange.
TO INSTALL SUPPLY SHUT-OFF VALVE
Install the supply shut-off valve so it is 9" (22.9cm)
above the finished floor line, and 4-1/8" (10.5cm) to the
left of the closet flange centerline.
The centerline of the supply shut-off valve outlet should
extend 3-5/8" (9.2cm) from the finished wall. Install the
supply shut-off valve with the outlet vertical.
A
1010439-2-
T-Bolts
9"
(22.9cm)
12"
(30.5cm)
2
Closet Flange
Fig. #1
Closet Flange
Fig. #2
Supply Shut-Off
Valve
4-1/8"
(10.5cm)
Closet Flange
Centerline
Fig. #3