Begin, End and Duration

The [Beg], [End] and [Dur] keys are
used to calculate the duration (time
elapsed) between dates or time.
Scheduling
Exercise 1
How many days will you work from
March 3, 1997 to August 12, 1997, if a
work week is 5 days? If you work another
45 days what is the new end date?
Steps/Keystrokes
1. Clear calculator:
[On/C] [On/C]
2. Set Mode to "WORK Act: Act" :
[Mode] until . . .
3. Find the number of days from
March 3, 1997 to August 12, 1997:
3 [//] 3 [//] 97 [Beg]
8 [//] 12 [//] 97 [End]
[Dur]
4. Find the new end date:
[Rcl] [End] [+] 45 [Day]
[=]
WORK
3•03•1997
BEG
8•12•1997
END
DUR
10•14•1997
TUE
Owner's Manual—29
Display
0.
Act: Act
116
DY