LG Multi F A2UW14GFA0 Engineering Product Data Book page 331

Heat pump 50hz/r410a
Table of Contents

Advertisement

2. Guideline for each installation process
2.9.3 Transfer to customer with explanation
Operational step
Complete test run
① The measurements taken during the test run should be recorded and kept on a test run inspection sheet.
② Do not forget to record the length of the refrigerant piping and the refrigerant additional charging volume on the plate on
the back of the outdoor unit external notice board, as this information will be required for servicing the system.
③ Explain to the customer how to operate and maintain the equipment and let him try it.
④ Assemble all the relevant diagrams and other printed matter which is required to operate the system and hand over to
the customer (on the spot) and request him to keep it handy.
⑤ Service contact address.
List of equipment which has been delivered
Installation drawing
1 set of operation manuals
Names of those responsible for the
work (emergency contact address)
Equipment guarantees.
Make final report
(test run
inspection sheet)
Explain how to
operate and
maintain equipment
It is essential to prepare a control wiring diagram
which clarifies the refrigerant system and the
control system.
Heat pump 50Hz/R410A
Hand over
relevant printed
materials
_ 36