Get/Put Test

The Get/Put test performs the following tasks:
Performs a Get/Put of a scratch tape in the top and bottom slots of each magazine that supports
the scratch tape's media
Performs a Get/Put of existing media if no scratch tape is found or if the top or bottom is occupied
Moves a scratch tape to one row in each frame to test cross-frame alignment
Uses a scratch tape to perform a Get/Put in each compatible drive

Picker Assembly Test

The picker assembly test performs the following tasks:
Performs pivot left and right check
Performs reach and retract five times
If the LMC gets its side done, performs a Get/Put of the selected cell
Scans the control module serial number to make sure the scanner is reading properly

I/E Station Assembly Test

The I/E station assembly test performs the following tasks:
Locks and unlocks I/E station
Calibrates each I/E station and check offsets collected
Checks each magazine's fiducial in the I/E station
Performs Get/Put tests on all the I/E station cells

Scanner Fiducial Test

The scanner fiducial test performs the following tasks:
Scans and checks each magazine fiducial
Scans and checks each drive sled fiducial
Tests the calibration sensor
Calibrates and checks repeatability, up to three times for marginal and failed calibration targets

Library Inventory

This inventory list provides the following statistical information:
Frame card serial numbers
Power supply serial numbers
Number of cartridges in the library
Controller serial number and firmware information for the following:
Management control blade
Control management blade
Robotic control unit or RCU
Picker
Scalar i6000 Installation Guide