MOVING THE CHILLER

Prior to moving the unit, ensure that the installation
site is suitable for installing the unit and is easily ca-
pable of supporting the weight of the unit and all as-
sociated services.
The unit must only be lifted by the base
frame at the points provided. Never move
the unit on rollers, or lift the unit using a
forklift truck.
Care should be taken to avoid damaging the condenser
cooling fins when moving the unit.
UNIT REMOVAL FROM SHIPPING
CONTAINER
1. Place a clevis pin into the holes provided at the
end of each base rail on the unit. Attach chains or
nylon straps through the clevis pins and hook onto
a suitable lift truck for pulling the unit out of the
container.
2. Slowly place tension on the chains or straps until
the unit begins to move and then slowly pull the
unit from the container. Be sure to pull straight so
the sides do not scrape the container.
3. Place a lifting fixture on the forks of the lift truck
and reattach the chain or strap. Slightly lift the
front of the unit to remove some weight from the
floor of the container. Continue pulling the unit
with an operator on each side to guide the lift
truck operator.
4. Pull the unit until the lifting locations are outside
of the container. Place 4 X 4 blocks of wood under
the base rails of the unit. Gently rest the unit on
the blocks and remove the chains and lift truck.
5. Attach lifting rigging from the crane and slowly
complete the removal from the container then lift
up and away.
6

LIFTING USING LUGS

Units are provided with lifting holes in the base frame
which accept the accessory lifting lug set as shown in
the figure below. The lugs (RH and LH) should be in-
serted into the respective holes in the base frame and
turned so that the spring loaded pin engages into the
hole and the flanges on the lug lock behind the hole.
The lugs should be attached to the cables/chains using
shackles or safety hooks.
LUG
LOCKING PIN

LIFTING USING SHACKLES

The shackles should be inserted into the respective
holes in the base frame and secured from the inside.
Use spreader bars to avoid lifting chains hitting the
chiller. Various methods of spreader bar arrangements
may be used, keeping in mind the intent is to keep the
unit stable and to keep the chains from hitting the chill-
er and causing damage.
Never lift the chiller using a forklift or by hooking to
the top rails. Use only the lifting holes provided.
Lifting Instructions are placed on a label on the chiller
and on the shipping bag.
During this procedure operators will be exposed to
lethal voltages and the operators must be qualified to
complete wiring work under these conditions. Risk as-
sessments should be conducted to ensure all appropri-
ate precautions are taken. The operators must comply
with all of Johnson Controls, Inc, electrical safety re-
quirements including "Lock-Out/Tag-Out" procedures
and wearing PPE (Personal Protective Equipment)
gear prior to performing the procedure.
LD19197a
CORRECT
LIFTING HOLE
IN BASE FRAME
FLANGE
LOCKING PIN
LIFTING HOLE
IN BASE FRAME
LUG
LOCKING
PIN
INCORRECT
LUG
FLANGE
FLANGE
LD19197b
JOHNSON CONTROLS

Advertisement

Table of Contents
loading

This manual is also suitable for:

Hfc-513a

Table of Contents