Two-Post Flush-Mount Configuration - Dell Neworking S6000-ON Installation Manual

Open networking
Hide thumbs Also See for Neworking S6000-ON:
Table of Contents

Advertisement

Figure 6. 1U tool-less configuration
2
Align and seat the front flange pegs in the holes on the front side of the vertical post, item 2.
3
Repeat this procedure for the second rail.
4
To remove each rail, pull on the latch release button on each flange ear and unseat each rail, item 3.

Two-post flush-mount configuration

CAUTION:
Your system is not NEBS Earthquake Z4-compliant if you use this installation method.
1
Remove the tool-less latch castings from the front side of each ReadyRails assembly, item 1.
Use a Torx driver to remove the two screws from each front flange ear on the switch side of the rail. Remove each latch casting.
Retain the castings for future rack requirements. It is not necessary to remove the rear flange castings.
S6000–ON installation