Maintenance Schedule

Monthly:
1.
Re-torque the anchor bolts to 86 foot pounds.
2.
Check all fi ttings, bolts and pins to insure proper mounting.
Note: All anchor bolts should take full torque. If any of the bolts does
not function for any reason, DO NOT use the lift until the bolt has been
replaced.
3.
Make a visual inspection of all hydraulic hoses/lines for possible wear or
leakage.
4.
Adjusting the lifting level on both platforms.
5.
Lubricate all moving parts with lubricant (Sea Fig. 39-42).
For Main Cylinder
For pins of connecting
platforms and scissors
Maintenance Schedule
Fig. 39
Fig. 41
For shaft of piston
rod of Main cylinder
For pins of connecting
platforms and scissors
PX-16A
Fig. 40
Fig. 42