Recalibration - Siemens SITRANS WW100 Operating Instructions Manual

Weighfeeders
Hide thumbs Also See for SITRANS WW100:
Table of Contents

Advertisement

Commissioning
7.9 Load cell replacement
7.9.3

Recalibration

1. Power up the integrator and using the appropriate integrator menu, verify that the new load
cell(s) are operating correctly.
2. Zero calibrate the unit using the integrator manual for reference. Record zero calibration
procedure results.
3. Span calibrate the unit using the integrator manual for reference. Record span calibration
procedure results.
4. Re-check zero calibration. Run another zero calibration and record the results. Verify that
the zero repeated to the same value recorded in step 2.
5. Confirm calibration with material test as described in the integrator manual, if possible,
before placing the weighfeeder back in operation.
34
Operating Instructions, 06/2018, A5E33560618-AC
SITRANS WW100

Advertisement

Table of Contents
loading

Table of Contents