4.5. SYSTEM CHARGING

Before commencing the charging procedure position the main iso-
lator of the unit in the OFF position.
1. Ensure that the system drain valve is closed
2. Open all the system air vents and of the terminal units
3. Open the system isolating valves
4. Start fi lling slowly opening the system water charging valve
external to the unit
5. When water exits the terminal units air vents close them and
continue charging until the required system operating pressure
is reached.

4.6. SYSTEM DRAINING

1. Before commencing draining the draining procedure position
the main isolator of the unit in the OFF position
2. Ensure the system water charging valve is closed
3. Open the system drain valve external to the unit and all the
system air vents and of the terminal units.
4. TYPICAL FYDRAULIC CIRCUITS
25