Quick Guide for Commissioning
1
Installation
§ Connect power (24VDC)
§ Connect the detector lines
§ Connect reset input (if S3 = ON)
§ Install the detector bases and the smoke detectors
§ Prepare for operation with 1 or 2 pipe systems
§ Connect pipe system or test pipe
2
Set Up
Set DIP switches S2 on pcb E596 according to tables below:
Air flow monitoring
Switch S2
delay time
A(1)
B(2)
OFF
ON
short
ON
OFF
middle
ON
ON
long
OFF
OFF
very long
Fault
Switch S3
OFF
Fault not latching
ON
Fault latching until reset
Atmospheric pressure compensation
R28
MP1 (+)
MP2 (-)
3
Commissioning
Initializing of airflow monitoring
1.
press button S1 "Init" several times:
for 1 tube system:
for 2 tube systems:
2.
Fix cover and tighten screws
3.
Initialization active
4.
Unit ready
Switch S2
C(3)
30 s
ON
2 min. (standard)
OFF
15 min.
OFF
1 h
ON
(standard)
see correction table for atm.pressure
green LED and yellow LED left flashes
green LED und yellow LEDs left and right flashes
within the next 2 min.
ca. 20 min., green and yellow LED flashing
green LED on
Fire & Security Products
Range
D(4)
OFF
small
I
ON
middle
II
OFF
large
III
(standard)
ON
very large
IV
or
2,50 V (standard)
Siemens Building Technologies Group

Advertisement

loading

Summary of Contents for Siemens AD2-C11

  • Page 1 LED und yellow LEDs left and right flashes Fix cover and tighten screws within the next 2 min. Initialization active ca. 20 min., green and yellow LED flashing Unit ready green LED on Fire & Security Products Siemens Building Technologies Group...
  • Page 2 +24V +24V Speisung Supply 24 VDC +ext. Alarm AD2-C11 -ext. Alarm Siemens Building Technologies AG Alte Landstrasse 411 CH-8708 Männedorf Tel. +41 1 - 922 61 11 Fax +41 1 - 922 64 50 www.cerberus.ch Document no. e4161b Manual - Edition 07.2001...