Carrier 19PV550 Installation, Operation And Maintenance Instructions

Hide thumbs Also See for 19PV550:
Table of Contents

Advertisement

Quick Links

I N S TA L L AT I O N ,
O P E R AT I O N
M A I N T E N A N C E
Nominal cooling capacity 550 - 1600 kW 50Hz
A N D
I N S T R U C T I O N S
19PV
Original document
Original document

Advertisement

Table of Contents
loading

Summary of Contents for Carrier 19PV550

  • Page 1 I N S TA L L AT I O N , O P E R AT I O N A N D M A I N T E N A N C E I N S T R U C T I O N S 19PV Nominal cooling capacity 550 - 1600 kW 50Hz Original document...
  • Page 2: Table Of Contents

    2.1 - Check equipment received ................................8 2.2 - Moving and siting the unit................................8 3 - DIMENSIONS, CLEARANCES ..............................9 3.1 - 19PV550 to 800................................... 9 3.2 - 19PV900 to 1180 ..................................10 4 - PHYSICAL AND ELECTRICAL DATA ............................12 4.1 - Physical data .....................................
  • Page 3 CONTENT 12 - OPTIONS ....................................28 13 - STANDARD MAINTENANCE ..............................29 13.1 - Level 1 maintenance ................................29 13.2 - Level 2 maintenance ................................29 13.3 - Level 3 (or higher) maintenance.............................. 29 13.4 - Tightening of the electrical connections ..........................29 13.5 - Tightening torques for the main bolts and screws ........................
  • Page 4: Introduction

    1 - INTRODUCTION The 19PV units are designed to cool water for the air conditioning In accordance with the Pressure Equipment Directive and of buildings and industrial processes. national usage monitoring regulations in the European Union the protection devices for these machines are classified as Prior to the initial start-up of the 19PV units, the people involved follows: in the on-site installation, start-up, operation, and maintenance of...
  • Page 5: Equipment And Components Under Pressure

    1 - INTRODUCTION These pipes must be installed in a way that ensures that Equip the engineers that work on the unit as follows: people and property are not exposed to refrigerant leaks. Operations Personal protection These fluids may be diffused in the air, but far away from any Maintenance, Welding or equipment (PPE)
  • Page 6: Repair Safety Considerations

    1 - INTRODUCTION • Carry out periodic leak tests. In the European Union, - Check the cut-off value article 2 of regulation (EU) No.517/2014 makes these - Reactivate manually HP switch and reactivate HP soft value" mandatory and sets their frequency. The table below - Repeat the procedure for each unit compressor.
  • Page 7 1 - INTRODUCTION CAUTION: RISK OF EXPLOSION: Only use refrigerant R134a, in accordance with AHRI 700-2014 (Air conditioning, Heating and Refrigeration Institute). The Do not use oxygen to purge lines or to pressurize a machine use of any other refrigerant may expose users and operators for any purpose.
  • Page 8: Preliminary Checks

    2 - PRELIMINARY CHECKS 2.1 - Check equipment received 2.2.3 - Checks before system start-up - Inspect the unit for damage or missing parts. If damage is Before the start-up of the refrigeration system, the complete detected, or if shipment is incomplete, immediately file a claim installation, including the refrigeration system must be verified with the shipping company.
  • Page 9: Dimensions, Clearances

    3 - DIMENSIONS, CLEARANCES 3.1 - 19PV550 to 800 COOLER CONDENSER Dimension (mm) 19PV 3045 1120 1745 2800 3070 1155 1846 2800 3270 1190 1925 3000 Legend: All dimensions are given in mm. Services clearances required Space required to remove cooler tubes...
  • Page 10: 19Pv900 To 1180

    3 - DIMENSIONS, CLEARANCES 3.2 - 19PV900 to 1180 COOLER CONDENSER Dimension (mm) 19PV 4257 1290 1955 3950 1010 4257 1290 1955 3950 1180 4257 1290 1955 3950 Legend: All dimensions are given in mm. Services clearances required Space required to remove cooler tubes Electrical box Inlet water Outlet water...
  • Page 11 3 - DIMENSIONS, CLEARANCES 3.3 - 19PV1300 to 1600 COOLER CONDENSER Dimension (mm) 19PV 1300 4705 1290 1955 4400 1450 4740 1290 2011 4400 1600 4740 1325 2065 4400 Legend: All dimensions are given in mm. Services clearances required Space required to remove cooler tubes Electrical box Inlet water Outlet water...
  • Page 12: Physical And Electrical Data

    4 - PHYSICAL AND ELECTRICAL DATA 4.1 - Physical data 19PV 1010 1180 1300 1450 1600 Sound levels - standard unit Standard unit Sound power dB(A) Sound pressure at 10 m dB(A) Dimensions Standard unit Length 3140 3160 3360 4345 4345 4345 4800...
  • Page 13: Electrical Data

    4 - PHYSICAL AND ELECTRICAL DATA 4.2 - Electrical data 19PV 1010 1180 1300 1450 1600 Power circuit supply Nominal voltage V-ph-Hz 400-3-50 Voltage range 360-440 Control circuit supply 24 V via internal transformer Maximum operating input power - Standard unit Circuit 1 Circuit 2 Unit with option 81...
  • Page 14 4 - PHYSICAL AND ELECTRICAL DATA Electrical data notes and operating conditions, 19PV units • As standard: 4. Overcurrent protection of the power supply conductors is not provided with the unit. 19PV 550 to 19PV 800 units have a single power connection point located 5.
  • Page 15: Electrical Connection

    Please refer to the certified dimensional drawings, supplied with the unit. Units Connection points 5.1 - Power supply 19PV550 to 800 1 per unit The power supply must conform to the specification on the unit 1 for circuit A 19PV900 to 1600 nameplate.
  • Page 16: Power Cable Entry

    5 - ELECTRICAL CONNECTION Minimum and maximum connectable wire sections for 19PV units Calculation of favourable case: Calculation of unfavourable case: - Perforated horizontal conduit Max. connectable - Closed conduit (standardised routing No. 41) (standardised routing No. 13) wire section - 70°C insulated cable if possible - 90°C insulated cable - Copper conductor (Cu)
  • Page 17: Application Data

    6 - APPLICATION DATA 6.1 - Operating limits for 19PV units 6.3 - Maximum chilled water flow The maximum chilled water flow is limited by the permitted pressure 19PV Minimum Maximum drop in the evaporator. It is provided in the table in chapter 6.6 - Select the option 100C that will allow a higher maximum water Evaporator flow rate (see the option 100C in the table in chapter 6.5).
  • Page 18: Standard And Optional Number Of Water Passes

    6 - APPLICATION DATA 6.5 - Standard and optional number of water passes 19PV 1010 1180 1300 1450 1600 Evaporator Standard Evaporator with option 100C Condenser Standard Condenser with option 102C 6.6 - Min water volume and evaporator & condenser water flow rates These below values are given for standard units.
  • Page 19: Evaporator Pressure Drop Curves

    6.8 - Evaporator pressure drop curves Units with two evaporator passes (standard) Units with one evaporator pass (option 100C) C D E F G Water flow rate, l/s Water flow rate, l/s Legend Legend 19PV550 19PV1180 19PV550 19PV1180 19PV720 19PV1300 19PV720 19PV1300...
  • Page 20: Water Connections

    7 - WATER CONNECTIONS ATTENTION: Before carrying out any water connections The manufacturer recommendations on heat exchange fluids: install the water box purge plugs (one plug per water box in - No NH ammonium ions in the water, they are very the lower section - supplied in the control box).
  • Page 21: Water Connections

    7 - WATER CONNECTIONS 7.2 - Water connections The water connections are Victaulic type connections. The inlet and outlet connection diameters are identical. Inlet/outlet diameters 19PV 1010 1180 1300 1450 1600 Evaporator Units without evaporator with one pass less (option 100C) Nominal diameter Actual outside diameter 168,3...
  • Page 22: Operation Of Two Units In Master/Slave Mode

    7 - WATER CONNECTIONS 7.5 - Operation of two units in master/slave mode The control of a master/slave assembly is in the entering water and does not require any additional sensors (standard configuration). It can also be located in the leaving water. In this case two additional sensors must be added on the common piping. All parameters, required for the master/slave function must be configured using the MST_SLV menu.
  • Page 23: Unit With Option 322

    8 - UNIT WITH HEAT PUMP APPLICATION (OPTION 322) The physical data, electrical data, dimensions & clearances are the same as standard 19PV units. Unlike in the cooling mode, the unit uses the heating setpoint in this configuration. The evaporator leaving water control (lowest setpoint taken into consideration) is still maintained to prevent operation at very low temperatures.
  • Page 24: Unit Operation With Option 154

    9 - UNIT OPERATION WITH OPTION 154 9.1 - Operating principle 9.4 - Fan stage assignment The units have been designed to optimise the operation of The minimum configuration of the number of fan stages is 2 for systems, using drycoolers as heat rejection system. correct operation.
  • Page 25: Unit Operation With Option 313

    10 - UNIT OPERATION WITH OPTION 313 10.1 - Operating principle The drycooler (with option 313) : - AUX board with the I/O The units have been designed to optimize the operation of - OAT sensor to be place in outdoor zone. systems, using drycoolers as free cooling system (method using - Dry Cooler Leaving Water Temperature (factory mounted) low outdoor air temperature to chill the water of the air conditioning...
  • Page 26: Major System Components And Operation Data

    11 - MAJOR SYSTEM COMPONENTS AND OPERATION DATA 11.1 - MagLev centrifugal compressor 11.1.5 - EMC Filter - 19PV units use TT (Twin-Turbine) MagLev centrifugal The EMC filter reduces electrical noise on the power lines compressors equipped with an inlet guide valve and (conducted emissions), it is located close to the compressor to controlled by a speed variator.
  • Page 27: Disconnect Switches For Power Supply

    11 - MAJOR SYSTEM COMPONENTS AND OPERATION DATA Corrosion allowances: After removing the lock, the motor mechanism must be switch in “Auto” position before to supply the unit. Gas side: 0 mm The command of the main supply disconnect switch closure is Heat exchange fluid side: 1 mm for tubular plates in lightly alloyed ensured by the software using the motor mechanism module when steels, 0 mm for stainless steel plates or plates with copper-nickel...
  • Page 28: Options

    12 - OPTIONS Option Description Advantage Use 19PV Low noise level Discharge piping acoustic insulation Up to 3 dB(A) quieter than standard unit 0550-1600 Unit equipped with supplementary water outlet Optimised operation of two units connected temperature sensor kit (to be field installed) Master/slave operation in parrallel operation with operating time 0550-1600...
  • Page 29: Standard Maintenance

    13 - STANDARD MAINTENANCE 13.3 - Level 3 (or higher) maintenance Air conditioning equipment must be maintained by professional technicians, whilst routine checks can be carried out locally by See note below. specialised technicians. See the standard EN 378-4. The maintenance at this level requires specific skills/approval/ Simple preventive maintenance will allow you to get the best tools and know-how and only the manufacturer, his representative performance from your HVAC unit:...
  • Page 30: Tightening Torques For The Main Bolts And Screws

    13 - STANDARD MAINTENANCE 13.5 - Tightening torques for the main bolts and screws Screw type Used for Torque Value (N.m) M20 nut Chassis M20 nut Heat exchanger side-side connection M16 nut Heat exchanger connection M10 nut Compressor fixing H M16 screw Heat exchanger water boxes, structure Thx M16x65 screw Compressor suction flanges...
  • Page 31: Start-Up Checklist For 19Pv Liquid Chillers (Use For Job File)

    14 - START-UP CHECKLIST FOR 19PV LIQUID CHILLERS (USE FOR JOB FILE) Preliminary information Job name: ........................................ Location: ........................................Installing contractor: ....................................Distributor: ....................................... Unit Model: ....................Compressors Circuit A Circuit B Model number.................. Model number ................Serial number .................. Serial number ................Motor number ..................
  • Page 32 14 - START-UP CHECKLIST FOR 19PV LIQUID CHILLERS (USE FOR JOB FILE) Unit start-up All discharge and liquid line valves are open Locate, repair and mark all refrigerant leaks All suction valves are open, if used Checks have been carried out for any possible leaks. Unit has been leak checked (including fittings) - on the whole unit - at all connections Locate, repair, and report any refrigerant leaks ..........................
  • Page 34 CARRIER participates in the ECP programme for LCP/HP Check ongoing validity of certificate: www.eurovent-certification.com Order No.: 10266, 03.2018. Supersedes order No.: New. Manufactured by: Carrier SCS, Montluel, France. Manufacturer reserves the right to change any product specifications without notice. Printed in the European Union.

This manual is also suitable for:

19pv72019pv800

Table of Contents