Decommissioning The Machine; Re-Commissioning The Machine; Faults; Inspections In The Event Of Faults - Siemens SIMOTICS HV C Operating And Installation Instructions

Induction motor
Table of Contents

Advertisement

Operation

8.7 Decommissioning the machine

As such, you can determine whether the machine needs commissioning or any necessary
measures such as cleaning and/or drying the winding:
● Can the machine be put into operation?
● Must the windings be cleaned or dried?
Detailed information on testing and the limit values can be found here:
"Testing the insulation resistance and polarization index" (Page 41)
8.7
Decommissioning the machine
● Record the decommissioning steps. This log will be useful upon recommissioning.
● If the machine is going to be out of service for longer than six months, then take the
See also
Protection against corrosion (Page 38)
Securing the rotor (Page 31)
Storage (Page 33)
8.8

Re-commissioning the machine

When you re-commission the machine, proceed as follows:
● Study the record made when the machine was decommissioned, and reverse the measures
● Perform the measures listed in the "Commissioning" section.
See also
Commissioning (Page 69)
Decommissioning the machine (Page 80)
8.9

Faults

8.9.1

Inspections in the event of faults

Natural disasters or unusual operating conditions, such as overloading or short circuit, are
faults that overload the machine electrically or mechanically.
80
necessary measures for preservation and storage. Otherwise, the machine could be
damaged as a result of not being operated.
that were taken for conservation and storage.
SIMOTICS HV C 1NB1402-2AA84-4CA0-Z
Operating Instructions 06/2018