6 INSTALLATION CHECKLIST AND SYSTEM FILL FOR
STARTUP
Checks to be Performed
Check device for damage upon receipt
Install and align to server cabinet
Flexible hoses connected (optional) properly
Packaging removed from the Liebert DCD
All assembly tools removed
Bushings installed properly
Chilled water connections leak-proof / pressure-tested
Air bled from coil
Chilled water flow adjusted to proper flow rate
Condensate line connected (if applicable) and routed to a suitable drain
Unused server space is blocked with blanking panels
Top and bottom of server cabinet are blocked and any cable entries are sealed to minimize air leakage.
Location
Customer Site Name
Customer Site Address
Site Contact
Phone Number
Installer Name
Installer Address
Ambient Room
Temperature
Room Humidity at Site
of Commissioning
Vertiv | Liebert® DCD™ User Manual |
Done
(to be signed
upon completion)
Date
°F (°C)
% Relative Humidity
Remarks
Installer Signature
43