NotchFlo DST Valve
March 2011

Installation

WARNING
Always wear protective gloves, clothing, and eyewear when performing any installation operations to avoid personal
injury.
Personal injury or property damage caused by sudden release of pressure may result if the valve assembly is installed where
service conditions could exceed the limits given in table 1 or on the appropriate nameplates. To avoid such injury or
damage, provide a relief valve for over‐pressure protection as required by government or accepted industry codes and good
engineering practices.
Check with your process or safety engineer for any additional measures that must be taken to protect against process
media.
If installing into an existing application, also refer to the WARNING at the beginning of the Maintenance section in this
instruction manual.
WARNING
Some bonnet flanges have a tapped hole that was used to handle the bonnet during manufacture. Since this tapped hole
was not designed or intended to support the weight of the valve/bonnet assembly, do not use this tapped hole to lift the
valve assembly or personal injury may result from the assembly falling.
CAUTION
When ordered, the valve configuration and construction materials were selected to meet particular pressure, temperature,
pressure drop, and controlled fluid conditions. Since some body/trim material combinations are limited in their pressure
drop and temperature ranges, do not apply any other conditions to the valve without first checking with your Emerson
Process Management sales office.
1. Before installing the valve, inspect it to ensure that the valve body cavity is free of foreign material.
2. Clean out all pipelines to remove scale, welding slag, and other foreign materials before installing the valve.
3. Flow through the valve must be in the direction indicated by the flow arrow, which is cast on or attached to the
valve body.
4. Use accepted piping practices when installing the valve in the pipeline. For flanged valve bodies, use a suitable
gasket between the body and pipeline flanges.
5. Install a three‐valve bypass around the valve if continuous operation is required during maintenance.
6. If the actuator and valve body are shipped separately, refer to the actuator mounting procedure in the appropriate
actuator instruction manual.