Commissioning With Bop-2 Operator Panel; Quick Commissioning With The Bop-2 - Siemens CU240E-2 Operating Instructions Manual

Sinamics g120 control units
Hide thumbs Also See for CU240E-2:
Table of Contents

Advertisement

Commissioning

4.2 Commissioning with BOP-2 operator panel

4.2
Commissioning with BOP-2 operator panel
Plugging on an operator panel
Procedure
To plug an Operator Panel on the Control Unit, proceed as follows:
1. Locate the lower edge of the Operator Panel into the matching
recess of the Control Unit.
2. Plug the Operator Panel onto the inverter until the latch audibly
engages.
You have plugged an operator panel onto the Control Unit.
The operator panel is ready for operation when you connect the inverter
to the power supply.
4.2.1

Quick commissioning with the BOP-2

Starting quick commissioning
Preconditions
● The power supply is switched on.
● The operator panel displays setpoints and actual values.
Procedure
Proceed as follows to carry out quick commissioning:
Press the ESC key.
Press one of the arrow keys until the BOP-2 displays the "SETUP" menu.
To start quick commissioning, in the "SETUP" menu, press the OK key.
If you wish to restore all of the parameters to the factory setting before the quick
commissioning, proceed as follows:
1. Press the OK key.
2. Switchover the display using an arrow key: nO → YES
3. Press the OK key.
20
CU240B-2 and CU240E-2 Control Units
Compact Operating Instructions, 01/2017, A5E39910322B AA

Advertisement

Table of Contents
loading

This manual is also suitable for:

Cu240b-2

Table of Contents