Step 2 - Plan For Sequence Of Unit Installation; Curb- - Mount Installation; Pad- - Mount Installation; Frame- - Mount Installation - Bryant 581Jx14 series Installation Instructions Manual

Single package rooftop, gas heating / electric cooling with puron (r-410a) refrigerant size 14
Table of Contents

Advertisement

Table 1 – Operating Weights
581J*14
COMPONENT
Base Unit
Economizer
Vertical
Horizontal
Perfect Humidity™ System
Powered Outlet
Curb
14--- in/356 mm
24--- in/610 mm
Step 2 — Plan for Sequence of Unit Installation
The support method used for this unit will dictate different
sequences for the steps of unit installation. For example,
on curb- - mounted units, some accessories must be
installed on the unit before the unit is placed on the curb.
Review the following for recommended sequences for
installation steps.
Curb- - mounted installation —
Install curb
Install field- - fabricated ductwork inside curb
Install accessory thru- - base service connection package
(affects curb and unit) (refer to accessory installation
instructions for details)
Prepare bottom condensate drain connection to suit
planned condensate line routing (refer to Step 9 for
details)
Rig and place unit
Install outdoor air hood
Install condensate line trap and piping
Make electrical connections
Install other accessories
UNITS LB (KG)
1430 (649)
100 (45)
115 (52)
62 (28)
32 (15)
180 (82)
235 (107)
Pad- - mounted installation —
Prepare pad and unit supports
Check and tighten the bottom condensate drain
connection plug
Rig and place unit
Convert unit to side duct connection arrangement
Install field- - fabricated ductwork at unit duct openings
Install outdoor air hood
Install condensate line trap and piping
Make electrical connections
Install other accessories
Frame- - mounted installation —
Frame- - mounted applications generally follow the
sequence for a curb installation. Adapt as required to
suit specific installation plan.
Step 3 — Inspect Unit
Inspect unit for transportation damage. File any claim
with transportation agency.
Confirm before installation of unit that voltage, amperage
and circuit protection requirements listed on unit data
plate agree with power supply provided.
On units with hinged panel option, check to be sure all
latches are snug and in closed position.
Locate the carton containing the outside air hood parts;
see Figs. 11 & 12. Do not remove carton until unit has
been rigged and located in final position.
Step 4 — Provide Unit Support
Roof Curb Mount —
Accessory roof curb details and dimensions are shown in
Fig. 4. Assemble and install accessory roof curb in
accordance with instructions shipped with the curb.
NOTE: The gasketing of the unit to the roof curb is
critical for a watertight seal. Install gasket supplied with
the roof curb as shown in Fig. 4. Improperly applied
gasket can also result in air leaks and poor unit
performance.
7

Advertisement

Table of Contents
loading

Table of Contents