INDOOR UNIT
Maximum
Elevation -
Outdooor
Unit BELOW
Indoor Unit
Outside Unit BELOW Indoor Unit
Do not allow for excess length of line sets to be left rolled up as part of the
required distance, or in general. This will also cause additional performance issues.
System Size (KBtu)
024
036/048

Leak Test and Evacuation

Air and moisture remaining in the refrigerant system will
have undesirable effects as indicated below:
Pressure in the system rises
Operating current rises
Cooling or heating efficiency drops
Moisture in the refrigerant circuit may freeze
Water may lead to corrosion of parts in the refrigera-
tion system
The line set between the indoor and outdoor units
must be leak tested and evacuated to remove any non-
condensables and moisture from the system.

Leak Test

Use the following procedure to test for system leaks:
1. Connect the manifold gauge set and dry nitrogen gas
cylinder to the liquid and gas service ports.
2. Open valve on nitrogen cylinder.
3. Pressurize the system per the pressure test
specifications in "Table 5. Pressure Test Specifications".
4. Check that the system pressure remains stable. If
there is any movement check system for leaks.
5. After the system is found to be free of leaks:
Close valve on nitrogen cylinder
Table 4. Refrigerant Line Set Requirements
Maximum Line Set
Length
OUTDOOR UNIT
Minimum Line Set
Length - 10 ft. (3m)
Each system size has a line set length and vertical elevation parameters.
Line Set Diameters (in.)
Liquid
Gas
3/8
5/8
3/8
5/8
Maximum Line Set
Length
INDOOR UNIT
Outside Unit ABOVE Indoor Unit
IMPORTANT
Maximum Elevation
Outdoor Unit BELOW
Indoor Unit - Feet
(Meter)
82 ft. (25 m)
98 ft. (30 m)
Relieve the nitrogen pressure by: loosening the
charge hose connector at the nitrogen cylinder
When the system pressure is reduced to normal,
disconnect the hose from the cylinder
Table 5. Pressure Test Specifications
Bar
Psig
1
3
44
2
15
220
3
32
470
4
45
650
5
32
470
Use only oxygen-free nitrogen (OFN).

Triple Evacuation Procedure

A Micron or Torr gauge must be used for this procedure.
1. Discharge the oxygen-free nitrogen and evacuate the
system to a reading of 8000 Microns (8 Torr) using all
service valves.
2. Break the vacuum by allowing nitrogen into the port
connections (liquid and gas line pipes) until a positive
pressure is achieved.
3. Evacuate the system to a reading of 5000 Microns (5
14
Minimum Line Set
Length - 10 ft. (3m)
OUTDOOR UNIT
Maximum
Elevation -
Outdooor
Unit ABOVE
Indoor Unit
Maximum Elevation
Outdoor Unit ABOVE
Indoor Unit - Feet
(Meter)
82 ft. (25 m)
98 ft. (30 m)
kPa
Duration
303
Minimum of 10 minutes
1517
Minimum of 10 minutes
3241
Minimum of 10 minutes
1 hour. Stress test to prove the
4482
integrity of the complete installation.
24 hours. Lower system pressure
3241
test, after confirmation No. 4 was
successfully completed.
IMPORTANT
Maximum Line
Set Length - Feet
(Meters)
164 ft. (50 m)
213 ft. (65 m)

Hide quick links: