4-10. Positioning Jumper Links (230/400 VAC 3-Phase)

Tools Needed:
8mm / .315 in
OM-249 332 Page 18
1
!
Disconnect and lockout/tag-
out input power before in-
stalling or moving jumper
links. Follow established pro-
cedures regarding the install-
ation and removal of lockout/
tagout devices.
.
All units have jumper links pre-
set to 400V.
Check input voltage available at site.
1
Jumper Link Label
Check label − only one is on unit.
2
Jumper Links
Move jumper links to match input
voltage.
Close and secure access door. Fol-
low established lockout/tagout pro-
cedures to put unit in service.
2
230V
956142796_3-10_D
400V