Test Run and Final Check

• Before starting the test run, measure the voltage at the primary side of the safety breaker. Check that it is 220-240V.
• Check that all liquid and gas shut-off valves are fully open.
• Check that piping and wiring all match. The wiring error check can be conveniently used for underground wiring and other wiring
that cannot be directly checked.
1.

Wiring error check

• This product is capable of automatic correction of wiring error.
• Press the "wiring error check switch" on the outdoor unit service monitor
print board. However, the wiring error check switch will not function for
one minute after the safety breaker is turned on, or depending on the
outside air conditions (See NOTE 2.). Approximately 10–15 minutes
after the switch is pressed, the errors in the connection wiring will be
corrected.
The service monitor LEDs indicate whether or not correction is
possible, as shown in the table below. For details about how to read the
LED display, refer to the service guide.
If self-correction is not possible, check the indoor unit wiring and piping
in the usual manner.
LED
1
Status
Flashing
(One or more of LEDs 1 to 4 are ON)
Wiring correct example
Terminal block
From Room C
to the "kitchen"
NOTE:
1) For two rooms, LED 3 and 4 are not displayed, and for three rooms, LED 4 is not displayed.
2) If the outside air temperature is 5°C or less , the wiring error check function will not operate.
3) After wiring error check operation is completed, LED indication will continue until ordinary operation starts.
This is normal.
4) Follow the product diagnosis procedures. (Check the nameplate on the underside of the shut-off valve.)
15
2
3
4
All
Flashing
Automatic correction impossible
One after another
Automatic correction completed
Abnormal stop [NOTE. 4]
From Room B
to the "living room"
to the "children's room"
LED lighting sequence after a wiring correction.
Order of LED flashing: 2 ➝ 1 ➝ 3 ➝ 4
Message
From Room D
From Room A
to the "bedroom"
Wiring error check
Service PC-board
Wiring error
check switch
(SW3)
∗ The figure at left shows branch wiring.
■English

Advertisement

Table of Contents
loading

Table of Contents