Checkout Procedures

Manufacturer Recommendations

Frequency
Test Equipment
Revision A
Maintenance: Checkout Procedures
127(
Complete the checkout procedures with a Dash monitor connected to
the docking station.
GE recommends that you perform checkout procedures:
upon receipt of the device.
every twelve months thereafter, and
each time the main enclosure is disassembled or a circuit board is
removed, tested, or replaced.
127(
To troubleshoot operation problems, see Chapter 5,
"Troubleshooting".
The following table lists GE recommended test equipment, adaptors, and
cables you need to successfully complete the checkout procedures. The
checkout procedures are written for the test equipment in the following
table. If you use test equipment other than those GE recommends, you
may need to slightly modify some test steps.
Patient Simulators and Cables
ECG Test
Marq-I ECG Simulator (no longer available for ordering)
MarqII-KIT (includes CO injectate box)
MarqIII-KIT (includes CO injectate box)
127(
You can use a MarqI, MarqII, or MarqIII patient simulator or an
equivalent 12SL ECG patient simulator.
ECG Patient Cable
ECG Leadwire Set
Remote control, PN 418720-xxx, with an autoport to Mport adapter, PN 2001973-001
Auxiliary Test
Remote control, PN 418720-xxx, with an autoport to Mport adapter, PN 2001973-001
Dash Port 2 Docking Station
2000966-138
4-13