Daily Operation; Lifting Of The Pile - JUNTTAN PM 20L Operator's Manual

Table of Contents

Advertisement

JUNTTAN
6.5

DAILY OPERATION

Daily operation on the work site consists of traveling with the machine and performing
various tasks associated with lifting piles off the ground, positioning them and doing the
actual driving. The preferred way of doing each step is detailed in the sections below.
n ATTENTION
To rotate machinery deck the horizontal slide must be 150 mm out or leader foot lifted
up in order to go over tracks, otherwise the machine will damage.
When operating the machine do it in the most stable and fuel-saving manner which will
put the least strain on the machine. That way you will increase the life of the machine
and minimize the risks.
6.5.1

LIFTING OF THE PILE

Lifting of piles may be necessary to move them near piling rig or to unload them from a
lorry.
n DANGER
When lifting piles be careful not to exceed the capacity of the winches. Do not exceed
values which are given in load lifting tables. Make sure that there is nobody under the
pile while you lift it.
• Keep the telescope leader down.
• Keep the hammer as down as possible. If necessary hammer can be lifted to 3 m
height.
• Keep the horizontal slide maximum 300 mm out.
• Keep the leader foot as down as possible.
• If necessary leader foot can be lifted so that is possible to turn uppercarriage over
tracks.
• Do not exceed values which are given in load lifting tables.
• Attach chains or ropes to the pile lifting points according to the pile manufacturer's
instructions.
• Be careful that pile does not hit the machine or people on the work site when lifting
it.
• Lower pile to desired position carefully
Daily operation section
67

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the PM 20L and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents

Save PDF