Download Print this page

Larson Electronics Megatower RNT-WCDE-11-PLM50-6X500LTL-LED Operation Manual

Advertisement

Quick Links

Deploying Mast:
1.) Choose a location that is as close to level as
possible to position the trailer. Drop the trailer
from the tow vehicle using the two front leveling
jacks. Ensure that the safety chains and break-
away cable have been disconnected from the tow
vehicle.
2.) Once the trailer is disconnected from the hitch of
the tow vehicle, level the trailer front to back and
side to side. This is a very important step as the
level of the mast is critical when this unit is in
operation. There are (6) jacks on the trailer for
leveling purposes, three per side of the trailer,
and are welded to the body of the trailer. Drop
each jack as close to ground as possible and
hand crank until level.
3.) Deploy the outriggers by pulling the retainer pins
from the top up enough to release the outrigger,
then slide the outrigger outwards. Do not lock the
retainer pin in the up position when deploying
each outrigger in order for them to snap in place
and stop the outrigger from coming out all the
way.
There are multiple locking points to adjust the
length of each outrigger depending on the ground
surface you have to work with. Pull the outrigger
out until the retainer pin locks into the outrigger.
Drop each jack as close to ground as possible
and hand crank each outrigger until there is slight
Megatower Operation Manual
pressure on the jacks and no
gap in the outrigger. These
outriggers are for stabilization
and
are
not
purposes.
4.) Once the trailer is level and stabilizers are
deployed, unlatch the mast head by going to the
rear of the trailer and releasing the mast head
latch.
The pin will remain in the unlocked position
during operation.
Make sure pin is not engaged
before deployment of the mast. If the mast
head latch is not released, the mast will not
elevate up to its vertical position.
5.) At this point, locate the controls and verify that
the mast air valve is in the drain (open) position
(A). This valve is located inside the gray box
attached to the green control box.
B
A
A.
Mast Air Valve
B.
Compressor Switch
C.
Hydraulic Ram Pendant
for
leveling
Touching
C
Page 1 of 5

Advertisement

loading

Summary of Contents for Larson Electronics Megatower RNT-WCDE-11-PLM50-6X500LTL-LED

  • Page 1 Megatower Operation Manual pressure on the jacks and no Deploying Mast: gap in the outrigger. These 1.) Choose a location that is as close to level as outriggers are for stabilization possible to position the trailer. Drop the trailer leveling Touching from the tow vehicle using the two front leveling purposes.
  • Page 2 Megatower Operation Manual box should be blinking red. The mast will not elevate horizontally if this pin is engaged. Once you have verified that the… Trailer dropped from the tow vehicle Leveling jack are deployed and Trailer is level Outriggers are deployed Mast head is unlatched Generator is running Mast retainer pin is in the open...
  • Page 3 Megatower Operation Manual transport/storage. At this point, the mast is ready The mast can take up to 20 minutes to fully to be elevated. Press the up button on the deploy and it is normal for several compressor orange pendant and the mast will start to elevate cycles during this time.
  • Page 4 Megatower Operation Manual 3.) The mast should be in the lower position and ready to lay horizontally for transport. Remove Lowering the mast: the mast retaining pin located on the right side of 1.) When preparing to lower the mast, open the the green job box.
  • Page 5 Megatower Operation Manual 7.) At this point, the outriggers can be retracted. 8.) The trailer is now ready for hookup to a tow Ensure each outrigger locks into place and the vehicle. Once tied to a tow vehicle, raise all jacks have proper ground clearance.
  • Page 6: Mast Troubleshooting

    Megatower Operation Manual MAST TROUBLESHOOTING  No power to unit. o Check to ensure the generator is running. o Check main breaker switch at generator is turned ON. o Check breaker panel and ensure nothing has been tripped or is off. ...