Download Print this page
Siemens P1-400 Installation Instructions

Siemens P1-400 Installation Instructions

Panelboard kit, jd main breaker kit

Advertisement

Quick Links

NOTE: For both feed location configurations, the breaker handle must point upward when in the "ON" position.
SUPPORT
BARRIER
ORIENTATION
BREAKER
SUPPORT
UP
TOP FEED CONFIGURATION
BOTTOM FEED CONFIGURATION
Figure 2: Top & Bottom Feed Kit Configurations
NOTE: For both feed location configurations, the filler is oriented as shown, with the "MAIN" label
positioned above the breaker handle.
TOP FEED
Figure 3: Top & Bottom Feed Deadfront Filler Installation
These instructions do not purport to cover all details or variations in equipment, or to provide for every possible
contingency to be met in connection with installation, operation or maintenance. Should further information be
desired or should particular problems arise, which are not covered sufficiently for the purchaser's purposes, the
matter should be referred to the local Siemens sales office. The contents of this Instruction manual shall not
become part of or modify any prior or existing agreement, commitment or relationship. The sales contract
contains the entire obligation of Siemens. The warranty contained in the contract between the parties is the sole
warranty of Siemens. Any statements contained herein do not create new warranties or modify the existing
warranty.
Trademarks - Unless otherwise noted, all names identified by ® are registered trademarks of Siemens AG or
Siemens Industry, Inc. The remaining trademarks in this publication may be trademarks whose use by third
parties for their own purposes could violate the rights of the owner.
BREAKER
SUPPORT
(ALREADY
MOUNTED
TO BREAKER)
(NO NEED
TO SECURE
OR REMOVE)
BREAKER
SUPPORT
BREAKER
SUPPORT
(ALREADY
MOUNTED
TO INTERIOR)
(MUST BE
SECURED
TO BOTH
BREAKER
AND RAILS)
SUPPORT
SUPPORT
BARRIER
BARRIER
ORIENTATION
ORIENTATION
Figure 2A: Bottom Feed
for Pre-Installed Breaker
Kit Configuration
UP
BOTTOM FEED
-4-
s
P1-400 Panelboard Kit
MBKJD1A & MBKJD3A
JD Main Breaker Kit
(for use in Revised P1 Panelboards ONLY)
Also for JD
breaker kits
with breaker
INCLUDED.
Part numbers:
MBKJD1***A
MBKJD3***A
MBKJD12***A
MBKJD32***A
1
To confirm, note the part number of the panel (marked on the interior label).
If it ends in an "N" or a "T" it is a "Revised P1" and is compatible with this kit.
(For example: P1E42MC250A is an Original P1; P1E42MC250AT is a Revised P1)
Installation
Instructions
1
11-A-1115-01 Rev. 02

Advertisement

loading

Summary of Contents for Siemens P1-400

  • Page 1 Siemens sales office. The contents of this Instruction manual shall not become part of or modify any prior or existing agreement, commitment or relationship. The sales contract contains the entire obligation of Siemens.
  • Page 2 Installation Instructions The following instructions are for the installation of a Siemens JD main breaker kit in a 400 amp Revised P1 Panel- board. The parts provided in this kit are for connection to a 1-phase 2 or 3-wire system or to a 3-phase 3 or 4-wire Figure 1 system.

This manual is also suitable for:

Mbkjd3aMbkjd1a