7  Commissioning
7.4.3 Configuring Single Operation and Single-Cluster Operation
Configuration of single operation and single-cluster operation is performed using the QCG on the
Sunny Remote Control.
Requirements:
☐ The Sunny Remote Control must be connected.
☐ In a cluster, the Sunny Remote Control must be connected to the master.
☐ No Sunny Remote Control must be connected to the slave.
☐ The QCG must have been started.
☐ All off-grid inverters must be switched on, but not in operation.
1. Turn the button to the right and select New System.
2. Press the button.
3. Turn the button to the right until Y is flashing and press the button. This confirms your selection
of New System.
4. Setting the date:
• Select the 003.04 Dt parameter and press the
button.
• Set the day and press the button.
• Set the month and press the button.
• Set the year and press the button.
• Confirm the date with Y.
5. Setting the time:
• Select the 003.05 TM parameter and press the
button.
• Set the hour and press the button.
• Set the minutes and press the button.
• Set the seconds and press the button.
• Confirm the time with Y.
78
SI80H-60H-OffGrid-IA-en-11
SMA Solar Technology AG
Installation Manual