6.0 TEST AND INSPECTION PLAN

The test plan is derived from the Product Test Reference for XENIUM DB.
6.1

User Interface Test

Use the Test SIM card "SP" / Production to test the transceiver as follows :
With a fast charger connected with the PRODUCT's bottom connector, check the full scrolling from one mode to the
next when charging IGN (Ignition)-Battery.
6.2

RF Test

The radio test must be performed with a Digital Radio Test Set connected to the mobile RF connector with the
specific RF cable
PCC/VY/691/E/XENIUM989/0025/MLD/MLD
SERVICE REPAIR SUPPORT
PROCEDURE
♦ On/off Button
♦ LCD Backlight
♦ Keyboard Test
♦ Buzzer Test
♦ Audio Test
♦ Antenna Test (levels 5 &10)
♦ LCD
♦ LED Test (On/Off)
♦ IMEI
♦ Tester Status/Eeprom Status