Commissioning and Handover

Upon completion of the installation, allow a suitable period of time for any fire cement and mortar to
dry out. A small fire may then be lit and checked to ensure the smoke and fumes are taken from the
stove up the chimney and emitted safely to atmosphere. Do not run the stove at full output for at least
24 hours.
On completion of the installation and commissioning, ensure that the operating instructions and
operating tools for the stove are left with the customer. Ensure to advise the customer on the correct use
of the appliance with the fuels likely to be used on the stove and warn them to use only the
recommended fuels for the stove.
Advise the user on what to do should smoke or fumes be emitted from the stove.
The user should be warned to use a fireguard to BS 6539 in the presence of children, aged and/or infirm
persons.