Potterton Promax HE Store Installation & Servicing Instructions Manual page 28

Promax he store series condensing boilers with integrated hot water storage
Table of Contents

Advertisement

2.4 Condensate Drain Pipe
Before fitting, fill the condensate trap with water.
Fit the steady bracket (with round hole) for the
condensate trap to the lower pair of holes in the left hand
cylinder side panel. Snap the C-shaped bracket into the
groove in the condensate connector. Insert the
condensate trap into the steady bracket and fit the C-
shaped bracket to the upper pair of holes in the left hand
cylinder side panel.
Ensure that the washer seal is in place as indicated and
tighten the large nut.
The condensate pipe should be run in 21.5/22.0 mm
diameter plastic material suitable for operation at 60° C.
Solvent weld PVC overflow is recommended or a PP
system can be used. Copper tube must not be used. Do
not use push-fit plastic pipe.
Use the flexible pipe provided to connect to 21.5mm PVC
pipe; alternatively a Marley or Plumb Center elbow can
be used to direct the condensate pipe through the LH
side panel (see Fig. 10a). When using the Osma PVC
overflow system, a 3/4 -to-22mm adaptor No. 158 may be
required.
Internal pipework should have a bore diameter no smaller
than 14 mm.
External pipework should be kept to a minimum, and
have a bore diameter no smaller than 32 mm.
Ideally the condensate pipe should be run internally to
the house soil and vent stack or to a waste pipe.
Alternatively, the condensate may be discharged into the
rainwater system, or a purpose-built soakaway.
All connecting drainage pipework must have a fall of at
least 50 mm per metre run. It is recommended that the
pipe is insulated if run externally to minimise the effects
of freezing.
NOTE: Connection of a condensate pipe to a drain may
be subject to local building regulations.
Manual Air Vent
Using the manual air vent, thoroughly vent air from
top of the heat exchanger when filling the system to
save time during the boiler commissioning. Note: 1/4"
dia. manometer tube fits the manual vent.
Central Heating Pump & System By-pass
The central heating pump is factory fitted and an
automatic system by-pass is provided. The boiler can
be used in systems controlled by thermostatic radiator
valves (TRVs) but it is essential that the by-pass
isolating valve is fully open.
The circulating pressure and flowrate available for the
central heating system is shown opposite with the by-
pass in circuit.
28
Boiler
Condensate
Connection
Fill up the Condensate
Trap with water, then
fit to the boiler
Lower Nut
Optional
Route -
Condensate
Fig. 10a
Washer Seal
Condensate
Drain Pipe
500mm supplied
(suitable for 21.5mm
overflow pipe)
Promax Store
Optional
RWC
Route -
DHW
© Baxi Heating UK Ltd 2012