Section 3.4 Installing the Flow Sensor
1.
Install the Flow Sensor between the last piece of apparatus and the Cell (if installed after the Cell,
damage to the sensor may result). When possible, install on a horizontal pipe.
Mark two lines on the pipe 3 inches (~76 mm) apart and cut with a hacksaw or pipe cutters.
2.
3.
Clean and glue the "T" connector (included) to the pipe making sure that the threaded end with the
sensor is on the topside of the pipe.
4.
Be sure the arrow on the top of the Flow Sensor is pointing in the direction of flow, and that no glue
touches the paddle inside the sensor as it may cause it to jam.
Section 3.5 Mounting the Control Box
1.
It's important to identify and understand the
purpose of each cord at the bottom of your
Control Box. Please refer to the picture for cord
identification and application prior to mounting:
BONDING – Bonding is recommended and may
be required by local code. The bonding lug is
found on the bottom of the Control Box.
POWER CORD – Hardwire the power cable to
the time clock as indicated in the section titled
"Wiring the Control Box". Check label on side of
Control Box for the proper voltage specification
of your system (i.e. 120v or 240v)
FLOW SENSOR – The flow switch MUST BE
connected to the Control Box in order for the
system to work properly.
switch operation once installed.
CELL CONNECTORS – Connect the two black
wires from the Control Box to the two metal studs
on the sides of the Cell and tighten firmly with a
screwdriver by hand. See "Wiring the Control
Box" for further instructions.
Flow direction
Ensure proper flow