HP L1000 - 9000 - 0 MB RAM Manual page 28

Site preparation guide - rp5400
Hide thumbs Also See for L1000 - 9000 - 0 MB RAM:
Table of Contents

Advertisement

General Site Preparation Guidelines
Site Inspection
Table 1-5
Site Inspection Checklist (Continued)
Please check either Yes or No. If No, include comment# or date
16
Does the input frequency correspond to
equipment specifications?
17.
Are lightning arrestors installed inside the
building?
18.
Is power conditioning equipment installed?
19.
Is there a dedicated branch circuit for
equipment?
20.
Is the dedicated branch circuit less than 250
feet (72.5 meters)?
21.
Are the input circuit breakers adequate for
equipment loads?
Safety
No.
Area or condition
22.
Is there an emergency power shut-off switch?
23.
Is there a telephone available for emergency
purposes?
24.
Is there a fire protection system in the
computer room?
25.
Is antistatic flooring installed?
26.
Are there any equipment servicing hazards
(loose ground wires, poor lighting, etc.)?
Cooling
No.
Area or condition
Can cooling be maintained between 20 °C and
27.
55 °C (up to 5000 ft.)? Derate 1 °C/1000 ft.
above 5000 ft. and up to 10,000 ft.
Can temperature changes be held to 10 °C per
28.
hour with tape media? Can temperature
changes be held to 20 °C per hour without tape
media?
29.
Can humidity level be maintained at 40% to
60% at 35 °C noncondensing?
30.
Are air conditioning filters installed and clean?