5.2 Weekly schedule

Weekly schedule is effective in Windows and Linux operating systems.
To specify a weekly schedule
In the Schedule area, select the appropriate parameter as follows:
Every: <...> week(s) on: <...>
In the During the day execute the task... area, select one of the following:
Once at: <...>
Every: <...>
From: <...> Until: <...>
In the Effective... area, set the following settings:
From: <...>
To: <...>
Advanced scheduling settings are available only for machines registered on Acronis Backup &
Recovery 10 Management Server. To specify these settings, click Change in the Advanced settings
area.
All the settings you made are displayed in the Result field at the bottom of the window.
Examples
"One day in the week" schedule
Run the task every Friday at 10PM, starting from a certain date (say 05/14/2009) and ending after six
months.
The schedule's parameters are thus set up as follows.
1. Every: 1 week(s) on: Fri.
2. Once at: 10:00:00 PM.
3. Effective:
From: 05/13/2009. The task will be started on the nearest Friday at 10 PM.
To: 11/13/2009. The task will be performed for the last time on this date, but the task itself will
still be available in the Tasks view after this date. (If this date were not a Friday, the task would
be last performed on the last Friday preceding this date.)
This schedule is widely used when creating a custom backup scheme. The "One day in the week"-like
schedule is added to the full backups, while the incremental backups are scheduled to be performed
on workdays. For more details, see the Full and incremental backups plus cleanup example in the
Custom backup scheme (p. 121) section.
"Workdays" schedule
80
Specify a certain number of weeks and the days of the week you want the
task to be run. For example, with the Every 2 week(s) on Mon setting, the task
will be performed on Monday of every other week.
Set up the time at which the task will be run once.
Set up how many times the task will be run during the specified time interval.
For example, setting the task frequency to Every 1 hour From 10:00:00 AM
until 10:00:00 PM allows the task to be run 12 times from 10 AM to 10 PM
during one day.
Set up a date when this schedule will be enabled (an effective date). If this
check box is cleared, the task will be started on the nearest day and time you
have specified above.
Set up a date when this schedule will be disabled. If this check box is cleared,
the task will be run for an indefinite number of weeks.
Copyright © Acronis, Inc., 2000-2010

Advertisement

Table of Contents
loading

This manual is also suitable for:

Backup & recovery 10 server for linux

Table of Contents