3 Installation

3.1

GENERAL

This section gives details of the installation process for the Grant
EvoLink.
These installation instructions must be read in conjunction with:
The Grant Aerona³ air source heat pump installation
instructions (provided with the unit).
The installation instructions for the boiler.
Before starting to install the Grant EvoLink, please read the Health
and Safety information given in Section 8 of these installation
instructions.
Similarly, before staring any installation work on the Grant
Aerona³ air source heat pump, please read the Health and
Safety information given in Section 14 of the Aerona³ installation
instructions.
3.2

REGULATIONS AND STANDARDS

The installation of the Grant EvoLink, the Grant Aerona³ air source
heat pump and the existing boiler must be in accordance with the
following recommendations, as applicable:
Building Regulations for England and Wales, and Building
Standards for Scotland
Local Bylaws (check with the Local Authority for the area)
Water Supply (Water Fittings) Regulations 1999
MCS Installer Standards (if applying for the Renewable Heat
Incentive)
MIS3005-D The heat pump Standard (Design)
MIS3005-I The heat pump Standard (Installation)
MCS020 MCS Planning Standard
The installation should also be in accordance with the latest
edition of the following standards and Codes of Practice:
BS7671 and amendments
BS EN 12831
3.3

LOCATION

The Grant EvoLink is enclosed in a wall mounted casing designed
to be installed internally.
The wall onto which the EvoLink is to be fixed must be flat,
vertical and of a suitable construction firm enough to support the
weight of the unit.
Do NOT install the EvoLink in any of the following locations:
In damp conditions within the property, e.g. any locations
subject to steam and condensation such as a bathroom.
In a position subject to heat, e.g. above a boiler, cooker, or
radiator or where it will be in direct sunlight.
Where it can be reached and tampered with by children.
The EvoLink must be positioned such that there are sufficient
clearances all round it for installation, maintenance and to
allow the front cover to be removed. Refer to subsection 3.4 -

Clearances.

3.4
CLEARANCES
The minimum clearances given below must be used to enable the
EvoLink to be easily commissioned, serviced, and maintained.
Sides:
30mm
Above:
50mm
Below:
300mm
In front: 600mm
3.5

METERING

In order for the EvoLink touchscreen user interface to display the
electrical consumption of the heat pump (in kWh), an electricity
meter must be installed in the electrical supply to the heat pump.
Refer to Section 4.7 for details on the connection of an electricity
meter.
Page 6
3.6

SYSTEM CLEANING

! CAUTION !
Grant recommends that the existing system be thoroughly
cleaned prior to commencing the installation of the Grant
EvoLink.
For optimum performance, and to avoid the danger of dirt and
foreign matter entering the EvoLink and Aerona³ air source heat
pump, the complete heating system should be thoroughly flushed
out before starting the EvoLink installation.
This should be carried out in accordance with the guidelines given
in BS 7593 'Treatment of water in domestic hot water central
heating systems'. This must involve the use of a proprietary
cleaner, such as Sentinel X300 or X400 or Fernox Restorer.
Grant also strongly recommends that a Grant MagOne in-line
magnetic filter (or equivalent*) is fitted in the heating system
return pipework when the EvoLink is installed. This should
be installed and regularly serviced in accordance with the
filter manufacturer's instructions.
*As measured by Gauss. The Grant MagOne magnetic filter has a
Gauss measurement of 12000.
3.7

PIPE CONNECTIONS

The Grant EvoLink is supplied with the following five pipe
connections protruding vertically downwards through the casing
base panel – refer to Section 2.2 – Dimensions.
These connections are as follows – from left to right (viewed from
the front of the EvoLink):
Boiler flow connection – 22mm copper
Boiler return connection – 22mm copper
heat pump flow connection – 28mm copper
Heating system return connection – 22mm copper
Heating system flow connection – 28mm copper