Mountings are shipped completely assembled, ready to
install.
1. Locate mountings under equipment at positions
shown on tags or on VM layout drawings, or as indi-
cated on packing slip or correspondence.
2. Set mountings on subbase, shimming or grouting
where required to provide flat and level surface at
the same elevation for all mountings (1/4" maximum
difference in elevation can be tolerated). Support the
full underside of the base plate - do not straddle gaps
or small shims.
3. Unless specified, mountings need not be fastened
to floor in any way. If required, bolt mountings to floor
through slots.
4. Set the machine or base on the mountings. The
weight of the machine will cause the upper housing
FIG. 22 – TYPE CP MOUNTING
126
APPENDIX 1
INSTALLATION AND ADJUSTING INSTALLATIONS
TYPE CP MOUNTING
of the mount to go down, possibly resting on the lower
housing.
5. If clearance "X" is less than 1/4" on any mounting,
with wrench turn up one complete turn on the adjust-
ing bolt of each mounting. Repeat this procedure until
1/4", clearance at "X" is obtained on one or more
mountings.
6. Take additional turns on all mountings having less
than 1/4" clearance, until all mountings have at least
this clearance.
7. Level the machine by taking additional turns on all
mounts at the low side. Clearance should not ex-
ceed 1/2" - greater clearance indicates that mountings
were not all installed at the same elevation, and shims
are required. This completes adjustment.