To Install The Daikin Online Controller Application; Configuration; To Set A Different Address; Commissioning - Daikin ATXM25N2V1B Installer's Reference Manual

Hide thumbs Also See for ATXM25N2V1B:
Table of Contents

Advertisement

6.7.3
To install the Daikin Online Controller
application
1 Open:
▪ Google Play for appliances using Android.
▪ App Store for appliances using iOS.
2 Search for Daikin Online Controller.
3 Follow the directions on the screen to install.
7

Configuration

7.1

To set a different address

In case 2 indoor units are installed in 1 room, different addresses for
2 user interfaces can be set.
1 Remove the cover and the batteries from the user interface.
2 Cut the address jumper J4.
a
Address jumper J4
NOTICE
Be careful NOT to damage any of the surrounding parts
when cutting the address jumper.
3 Turn the power supply on.
4 Press
,
and
5 Press
, select
and press
Result: The operation lamp will start to blink.
CTXM15+ATXM20~50+FTXM20~71N2V1B
Daikin room air conditioner
4P518023-4C – 2018.09
a
simultaneously.
.
a
Operation lamp
b
Indoor unit ON/OFF switch
6 Press the indoor unit ON/OFF switch while the operation lamp
is blinking.
Address jumper
Factory setting
After cutting with nippers
INFORMATION
If the setting could NOT be completed while the operation
lamp was blinking, repeat the setting process from the
beginning.
7 When the setting is complete, keep
5 seconds.
Result: The user interface will return to the previous screen.
8

Commissioning

8.1

Overview: Commissioning

Typical workflow
Commissioning typically consists of the following stages:
1
Checking the "Checklist before commissioning".
2
Performing a test run for the system.
8.2

Checklist before commissioning

Do NOT operate the system before the following checks are OK:
You read the complete installation instructions, as
described in the installer reference guide.
The indoor units are properly mounted.
The outdoor unit is properly mounted.
Air inlet/outlet
Check that the air inlet and outlet of the unit is NOT
obstructed by paper sheets, cardboard, or any other
material.
There are NO missing phases or reversed phases.
The refrigerant pipes (gas and liquid) are thermally
insulated.
Drainage
Make sure drainage flows smoothly.
Possible consequence: Condensate water might drip.
The system is properly earthed and the earth terminals
are tightened.
The fuses or locally installed protection devices are
installed according to this document, and have NOT been
bypassed.
The power supply voltage matches the voltage on the
identification label of the unit.
The specified wires are used for the interconnection
cable.
The indoor unit receives the signals of the user interface.
a
There are NO loose connections or damaged electrical
components in the switch box.
b
The insulation resistance of the compressor is OK.