INSTRUCTIONS FOR PROVISIONS:
If straps are installed but the breaker will NOT be at this time, provision barriers MUST be installed.
(Skip this section if the breaker is installed.)
PREPARING THE EQUIPMENT FOR PROVISIONS:
(Refer to Figures 1 thru 5)
A. Follow Steps 1 thru 11 from page 2 and page 3
of this instruction sheet.
INSTALLING THE PROVISION STRAP BARRIER:
(Refer to Figure 7)
B. To install the Provision Barrier (Item 12), form the
barrier as shown, orient it as shown (longer side
towards inside), align the barrier hole with the
hole in the Medium Strap (Item 4), and secure
with the #10-32 screw (Item 14).
INSTALLING FILLER TO THE COVER PLATE:
(Refer to Figure 8)
C. Orient the Provision Filler Plate (Item 13) to the
Cover Plate (Item 6) as shown. (The Filler Plate
comes with a pre-applied label. That label should
face the exterior, and be oriented such that it can
be read when this assembly is installed onto the
deadfront supports.)
D. Secure the Provision Filler Plate (Item 13) to the
Cover Plate (Item 6) with a pair of Round Head
Screws (Item 15) and Locknuts (Item 16), one set
at each corner.
INSTALLING THE COVER PLATE:
(Refer to Figure 9)
E. Install the Cover Plate (Item 6) by aligning it
over the breaker mounting provision and loosely
secure it to the deadfront support rails with the four
1/4"-20 x 3/8" screws (Item 18).
F. Once all the covers are in place, tighten all the
fasteners to the torque specified on the rear of the
deadfront or noted in the table on page 2.
COMPLETING THE INSTALLATION:
G. Ensure that any bus or breaker hardware is
torqued as specified on the rear of the deadfront.
Then replace all the cover plates and gutter
covers. Finally, ensure any fillers are in place
BEFORE re-energizing the equipment.
These instructions do not purport to cover all details or variations in equipment, or to provide for every possible contingency to be met in connection
with installation, operation or maintenance. Should further information be desired or should particular problems arise, which are not covered sufficiently for
the purchaser's purposes, the matter should be referred to the local Siemens sales office. The contents of this instruction manual shall not become part of
or modify any prior or existing agreement, commitment or relationship. The sales contract contains the entire obligation of Siemens. The warranty
contained in the contract between the parties is the sole warranty of Siemens. Any statements contained herein do not create new warranties or modify the
existing warranty.
Trademarks - Unless otherwise noted, all names identified by ® are registered trademarks of Siemens AG or Siemens Industry, Inc. The remaining
trademarks in this publication may be trademarks whose use by third parties for their own purposes could violate the rights of the owner.
14
12
Figure 7
4
8
7
15
13
6
Figure 8
16
18
Figure 9
-4-
S
S3VA55TD
Distribution Switchboard
or P5 Power Panel
Strap Mounting Kit for
800A 3VA55/65 or 1000A 3VA66
Breaker in Unit Space
6
Installation
Instructions
11-B-1097-01 Rev. 00

Advertisement

loading

Summary of Contents for Siemens S3VA55TD

  • Page 1 Should further information be desired or should particular problems arise, which are not covered sufficiently for the purchaser’s purposes, the matter should be referred to the local Siemens sales office. The contents of this instruction manual shall not become part of or modify any prior or existing agreement, commitment or relationship.
  • Page 2 9. For three-phase installation ONLY: side Panel. It is for use with a Siemens Type 3VA55 (MMAS, HMAS or CMAS) or Type 3VA65 (MMAE, HMAE or CMAE) breaker (Skip to Step 10 for single-phase systems) as a Main or Branch device in an 800A application, or Type 3VA66 (MMNAE, HMNAE or CMNAE) breaker as a Main or Branch To install the (B-phase) Medium Strap (Item 4), locate device in a 1000A application.