Weights

Table 1. Maximum unit and corner weights (lb) and center of gravity dimensions (in.) cooling with optional electric
heat (Gas/Electric) units only
Tons
Unit Model No.
3
GBC036*
4
GBC048*
5
GBC060*
(a)
Weights are approximate.
(b)
Weights do not include additional factory or field installed options/accessories.
(c)
Corner weights are given for information only.
Figure 10. Corner weights
CENTER OF GRAVITY
LENGTH
CENTER OF
GRAVITY
WIDTH

Rigging

WARNING
Heavy Object!
Failure to follow instructions below could result in
unit dropping which could result in death or serious
injury, and equipment or property-only damage.
Ensure that all the lifting equipment used is properly
rated for the weight of the unit being lifted. Each of the
cables (chains or slings), hooks, and shackles used to
lift the unit must be capable of supporting the entire
weight of the unit. Lifting cables (chains or slings)
may not be of the same length. Adjust as necessary
for even unit lift.
WARNING
Improper Unit Lift!
Failure to properly lift unit in a LEVEL position could
result in unit dropping and possibly crushing
operator/technician which could result in death or
serious injury, and equipment or property-only
damage.
Test lift unit approximately 24 inches (61 cm) to verify
proper center of gravity lift point. To avoid dropping of
unit, reposition lifting point if unit is not level.
14
Weights (lb)
(a)
,
(b)
Shipping
Net
574
524
616
566
636
586
Corner Weights
(c)
A
B
C
95
111
172
110
119
175
120
125
174
Refer to
Figure 11, p. 14
weights rigging before proceeding.
1. Remove the shipping crate from around the unit. Do not
remove the crating from the top of the unit.
2. Rig the unit as shown in
adequate strength lifting slings to all four lifting brackets
in the unit base rail. Do not use cables, chains, or slings
except as shown.
3. Install a lifting bar, as shown in
protect the unit and to facilitate a uniform lift. The
minimum distance between the lifting hook and the top
of the unit should be 7 feet.
4. Test-lift the unit to ensure it is properly rigged and
balanced, make any necessary rigging adjustments.
5. Lift the unit and position it into place.
6. Downflow units; align the base rail of the unit with the
curb rail while lowering the unit onto the curb. Make
sure that the gasket on the curb is not damaged while
positioning the unit.
Figure 11. Rigging and center of gravity data
Center of Gravity (in.)
Length
D
Width
146
42
162
40
168
39
and for typical unit operating
Figure 11, p.
14. Attach
Figure 11, p.
CENTER OF GRAVITY
LENGTH
RT-SVX058G-EN
29
29
28
14, to
CENTER OF GRAVITY
WIDTH

Advertisement

Table of Contents
loading