T-STAT LOCATION

T-Stats are located within the electrical raceway.

Condensing Unit Installation Requirements

For proper operation of the Condensing Unit provide an
opening with adequate exhause and intake as follows:
Up to 1 1/2 hp: minimum of 2 vents totalling 150 sq. in.
Over 1/2 hp: minimum of 2 vents totalling 150 sq. in.
Self-Contained Model Installation - Low temperature
merchandisers need to be connected to both a 120V / 60
Hz and 230V / 60 Hz electrical supply.
PIPING
For merchandisers with "electric" defrost, the suction and
liquid lines should be clamped or taped together and
insulated for a minimum of 30 feet. For models with
®
"KOOLGAS
" defrost, suction, and liquid lines should not
contact each other, and should be insulated separately for
a minimum of 30 feet. With either type defrost, additional
insulation for the balance of the liquid and suction lines is
required wherever condensation and drippage would be
objectionable.
The refrigerant line outlets are located under the fixture
at the left end when viewed from the back. Insulate suction
lines to prevent condensation dripping on the floor.
8
IGSSB-SCSS / SCSS-SL-0108