Rheem 180 Owner's Manual And Installation Instructions page 68

Table of Contents

Advertisement

COMMISSIONING
INSTALLATION CHECKLIST
Prior to handover, complete the final check list:
1.
System is installed as per the installation instructions ......................................................................... [
2.
Water is connected, turned on and solar storage tank is filled ............................................................. [
3.
Closed circuit is filled with correct concentration of fluid and has been commissioned ......................... [
4.
All mechanical fixings are secured ..................................................................................................... [
5.
Collector rail has a rise of 12-15 mm per collector on the hot outlet side of the solar collectors
if installed directly onto the roof .......................................................................................................... [
6.
Collector rail is either horizontal or higher on the hot outlet side of the solar collectors
if part of a frame ................................................................................................................................. [
7.
Protective plastic film removed from tank (if fitted) .............................................................................. [
8.
Covers removed from collectors ......................................................................................................... [
9.
Pipe, conduit penetrations through the roof have been sealed correctly .............................................. [
10. Roof tiles put back into position .......................................................................................................... [
11. Roof flashing watertight ...................................................................................................................... [
12. System checked for water (and heating fluid) leaks and pipe connections are correctly tightened ....... [
13. Cold and hot water piping checked for water leaks ............................................................................. [
14. Drain pipes free of any obstruction ..................................................................................................... [
15. All pipe work clipped where necessary ............................................................................................... [
16. Electrical power to the booster is switched on (if required) .................................................................. [
17. Operation of booster checked ............................................................................................................ [
18. Air bled from taps ............................................................................................................................... [
19. Instruct the householder on the water heater system use and leave manual with the householder ...... [
68
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]