Unpacking The Product; Checking The Scope Of Delivery; Required Accessory; Installation Site - Vaillant ecoPOWER 3.0 /2 Installation And Maintenance Instructions Manual

Table of Contents

Advertisement

Transport the product using a fork-lift
truck that is suitable for the weight of the
product. Secure the product against slip-
ping and tipping over.
When lifting the product, use hoisting and
rigging gear that is suitable for the weight
of the product. Secure the rigging mater-
ial or hoist the product only in the load-
carrying area of the product, between the
product's feet. Secure the rigging gear
against slipping.
Caution.
Risk of motor damage when the maximum
lateral angle of inclination is exceeded.
Have the product at a maximum lateral
angle of inclination of up to 45°.
Load-carrying area (1) between the feet, to secure rigging
gear and to lift the product.
4.2

Unpacking the product

1.
Remove the protective film from all parts of the product.
2.
Remove the collapsible boxes and polystyrene sections
from the product.
4.3

Checking the scope of delivery

Check that the scope of delivery is complete and intact.
Number
Designation
1
ecoPOWER
7
VR 10 standard sensor
1
Condensate siphon
1
Square spanner for the side panels
1
NI 1000 room temperature sensor
1
VRC 693 outdoor temperature sensor
4
Absorption damper
0020241403_02 ecoPOWER 3.0 /2, ecoPOWER 4.7 /2 Installation and maintenance instructions
Number
Designation
Various
Operating instructions, installation and main-
tenance instructions, commissioning checklist,
service record
4.4

Required accessory

The following accessories are required for the installation:
Connection kit
Return retention group
Gas safety hose
Heating flow hose
Heating return hose
The following accessory is available for the optional remote
monitoring system:
VPN communication unit (requires Internet access)
4.5

Installation site

When selecting and equipping the installation room, observe
the national regulations, standards, directives and laws that
are relevant for operating heat production sources.
The product meets the requirements of Class A in accord-
ance with CISPR 11. The product may cause radio interfer-
ence in the living area.
During operation, the product generates various emissions
(heat, noise, etc.). For operation as intended and without dis-
ruptions, installation must therefore be carried out in a sep-
arate room in the cellar of the building. Other installations in
the same installation room as the product may be influenced.
4.5.1
Influence of the installation height on the
electrical power
The product's electrical power varies depending on the in-
stallation height.
Based on an environmental temperature of 20 °C and 100%
1
nominal output at sea level (0 m NHN (above sea level)), the
product has the following electrical power depending on the
installation height (above sea level):
Installation
VNC 88+3/2 elec-
height [m]
trical power
0
3.0 kW
500
2.8 kW
1000
2.7 kW
1500
2.5 kW
2000
2.3 kW
4.5.2
Sound insulation
Due to the operating noises that are produced, sound insula-
tion measures are particularly necessary when installing the
system in residential buildings, hotels, etc.
To isolate structure-borne sound, we recommend pla-
cing the product on a floor panel (base) that weighs at
least 400 kg and is separated from the rest of the building
structure.
Connect the product using the flexible connection pipes.
Equip the flue pipework at the chimney opening with an
insulation jacket (mineral wool).
Set-up 4
VNC 135+3/2 elec-
trical power
4.7 kW
el
el
4.4 kW
el
el
4.2 kW
el
el
3.9 kW
el
el
3.7 kW
el
el
7