Refrigerant Piping Work - Daikin CTXU25G2V1B Installation Manual

R410a split series
Hide thumbs Also See for CTXU25G2V1B:
Table of Contents

Advertisement

Refrigerant Piping Work

2.
Refrigerant piping.
CAUTION
1) Use the flare nut fixed to the main unit. (To prevent cracking of the flare nut by aged deterioration.)
2) To prevent gas leakage, apply refrigeration oil only to the inner surface of the flare. (Use refrigeration oil for R410A.)
3) Use torque wrenches when tightening the flare nuts to prevent damage to the flare nuts and gas leakage.
Align the centres of both flares and tighten the flare nuts 3 or 4 turns by hand. Then tighten them fully with the torque wrenches.
2-1. Caution on piping handling.
1) Protect the open end of the pipe against dust and moisture.
2) All pipe bends should be as gentle as possible. Use a pipe bender
for bending.
2-2. Selection of copper and heat insulation materials.
• When using commercial copper pipes and fittings, observe the following:
1) Insulation material: Polyethylene foam
Heat transfer rate: 0.041 to 0.052W/mK (0.035 to 0.045kcal/(mh•°C))
Refrigerant gas pipe's surface temperature reaches 110°C max.
Choose heat insulation materials that will withstand this temperature.
2) Be sure to insulate both the gas and liquid piping and to provide insulation
dimensions as below.
25/35/42 class
O.D. 9.5mm
30mm or more
3) Use separate thermal insulation pipes for gas and liquid refrigerant pipes.
7
[Apply oil]
Do not apply refrigeration
oil to the outer surface.
Flare nut
Do not apply refrigeration
oil to the flare nut avoid
tightening with over torque.
Gas side
25/35/42 class
3/8 inch
32.7-39.9N m
(330-407kgf cm)
Gas side
50 class
O.D. 12.7mm
Minimum bend radius
40mm or more
Thickness 0.8mm (C1220T-O)
Apply refrigeration oil to
the inner surface of the
flare.
Flare nut tightening torque
50 class
1/2 inch
49.5-60.3N m
(505-615kgf cm)
(144-175kgf cm)
Gas pipe thermal insulation
Liquid side
25/35/42 class
O.D. 6.4mm
I.D. 12-15mm
30mm or more
[Tighten]
Torque wrench
Spanner
Piping union
Flare nut
Liquid side
1/4 inch
14.2-17.2N m
Be sure to
place a cap.
Rain
If no flare cap is
available, cover the
flare mouth with
tape to keep dirt or
water out.
Finishing tape
Gas pipe
Gas pipe
insulation
Liquid pipe insulation
50 class
I.D. 14-16mm
Thickness 10mm Min.
Wall
Inter-unit wiring
Drain hose
Humidifying
hose
Liquid pipe
Liquid pipe
thermal insulation
I.D. 8-10mm
■English

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ctxu35g2v1bCtxu42g2v1bCtxu50g2v1b

Table of Contents