3 Preparation

3
Preparation
3.1

Preparing installation site

WARNING
The appliance shall be stored in a room without
continuously operating ignition sources (example: open
flames, an operating gas appliance or an operating electric
heater).
3.1.1
Installation site requirements of the
outdoor unit
Mind the spacing guidelines. See the "Technical data" chapter, and
the figures on the inside of the front cover.
INFORMATION
The sound pressure level is less than 70 dBA.
CAUTION
Appliance not accessible to the general public, install it in a
secured area, protected from easy access.
This unit, both indoor and outdoor, is suitable for

installation

in
a
commercial
environment.
4
Installation
4.1

Mounting the outdoor unit

4.1.1

To provide the installation structure

Prepare 4 sets of anchor bolts, nuts and washers (field supply) as
follows:
(mm)
a
Make sure not to cover the drain holes of the bottom plate
of the unit.
INFORMATION
The recommended height of the upper protruding part of
the bolts is 20 mm.
Installation manual
6
and
light
industrial
4× M12
a
NOTICE
Fix the outdoor unit to the foundation bolts using nuts with
resin washers (a). If the coating on the fastening area is
stripped off, the nuts rust easily.
a
4.1.2

To install the outdoor unit

4.1.3

To provide drainage

INFORMATION
If necessary, you can use a drain plug kit (field supply) to
prevent drain water from dripping.
NOTICE
If drain holes of the outdoor unit are covered by a mounting
base or by floor surface, raise the unit to provide a free
space of more than 150 mm under the outdoor unit.
Drain holes (dimensions in mm)
A
160
620
B
36
61
262
416
595
A
Discharge side
B
Distance between anchor points
C
Bottom frame
D
Drain holes
E
Knockout hole for snow
Snow
In regions with snowfall, snow might build up and freeze between the
heat exchanger and the external plate. This might decrease the
operating efficiency. To prevent this:
1 Drill (a, 4×) and remove the knockout hole (b).
4× M12
160
C
D
E
RZAG71~140M_V1+Y1
Sky Air Alpha-series
4P485927-1 – 2017.04