Installation; Upflow Installation - Bryant 313AAV Installation, Start-Up, Operating And Service And Maintenance Instructions

Series 100/a 4-way multipoise induced-combustion gas furnace input capacities: 45,000 thru 135,000 btuh
Table of Contents

Advertisement

2
of at least 2 in.
/1,000 Btuh (4,400 mm
input rating of all gas appliances.
2. An attic or crawlspace may be considered a space that
freely communicates with the outdoors provided there are
adequate permanent ventilation openings directly to
outdoors having free area of at least 1- -in.
total input rating forall gas appliances in the space.
3. In spaces that use the Indoor Combustion Air Method,
infiltration should be adequate to provide air for
combustion, permanent ventilation and dilution of flue
gases. However, in buildings with unusually tight
construction, additional air MUST be provided using the
methods described in the Outdoor Combustion Air
Method section.
Unusually tight construction is defined as construction with:
a. Walls and ceilings exposed to the outdoors have a
continuous, sealed vapor barrier. Openings are gasketed
or sealed and
CIRCULATING AIR
DUCTS
INTERIOR
HEATED
SPACE
CIRCULATING AIR DUCTS
2
*Minimum opening size is 100 in.
with minimum dimensions of 3 in. (76
mm).
*Minimum of 3 in. (76 mm), when type ---B1 vent is used.
Fig. 8 - - Air for Combustion, Ventilation, and Dilution from
Indoors
b. Doors and openable windows are weatherstripped and
c. Other openings are caulked or sealed. These include
joints around window and door frames, between sole
plates and floors, between wall- -ceiling joints, between
wall panels, at penetrations for plumbing, electrical and
gas lines, etc.
Combination of Indoor and Outdoor Air
1. Indoor
openings
shall
Combustion Air Method below and,
2. Outdoor openings shall be located as required in the
Outdoor Combustion Air Method menioned previously
and,
3. Outdoor openings shall be sized as follows:
a. Calculate the Ratio of all Indoor Space volume divided
by required volume for Indoor Combustion Air
Method below.
2
/kW) of total
2
/4,000 Btuh of
VENT THROUGH ROOF
12" MAX
(305mm)
1 SQ IN.
PER 1000
BTUH* IN DOOR
OR WALL
UNCONFINED
SPACE
6" MIN
(152mm)
(FRONT)
Ü
1 SQ IN.
PER 1000
BTUH* IN DOOR
OR WALL
12" MA X
(305mm)
A03175
comply
with
the
Indoor
Fig. 9 - - Removing Bottom Closure Panel
b. Outdoor opening size reduction Factor is 1 minus the
Ratio in a. above.
c. Minimum size of Outdoor openings shall be the size
required in Outdoor Combustion Air Method above
multiplied by reduction Factor in b. above. The minimum
dimension of air openings shall be not less than 3 in. (80
mm).

INSTALLATION

UPFLOW INSTALLATION

Bottom Return Air Inlet
These furnaces are shipped with bottom closure panel installed in
bottom return- -air opening. Remove and discard this panel when
bottom return air is used. To remove bottom closure panel,
perform the following:
1. Tilt or raise furnace and remove two screws holding
bottom filler panel. (See Fig. 9.)
2. Rotate bottom filler panel downward to release holding
tabs.
3. Remove bottom closure panel.
4. Reinstall bottom filler panel and screws.
Side Return Air Inlet
These furnaces are shipped with bottom closure panel installed in
bottom return- -air opening. This panel MUST be in place when
only side return air is used.
NOTE: Side return- -air openings can be used in UPFLOW and
most HORIZONTAL configurations. Do not use side return- -air
openings in DOWNFLOW configuration.
Leveling Legs (If Desired)
In upflow position with side return inlet(s), leveling legs may be
used. (See Fig. 10.) Install field- -supplied, 5/16 x 1- -1/2 in. (8 x
38 mm) (max) corrosion- -resistant machine bolts, washers and
nuts.
NOTE: Bottom closure must be used when leveling legs are
used. It may be necessary to remove and reinstall bottom closure
panel to install leveling legs. To remove bottom closure panel, see
Item 1. in Bottom Return Air Inlet section.
To install leveling legs:
1. Position furnace on its back. Locate and drill a hole in
each bottom corner of furnace. (See Fig. 10.)
2. For each leg, install nut on bolt and then install bolt and
nut in hole. (Install flat washer if desired.)
3. Install another nut on other side of furnace base. (Install
flat washer if desired.)