Installation and Operating Instructions STORAGE-67-TS-10 ENGLISH STORAGE-67-TS-10 | Version 1.1...
Page 2
Legal Provisions The information provided in this document is the property of SMA Solar Technology AG. No part of this docu- ment may be reproduced, stored in a retrieval system or transferred in any form or by any means (electronically, mechanically by photocopying or recording) without the prior written permission of SMA Solar Technology AG.
8.1 Commissioning of a single unit ............. 30 8.2 Commissioning of STORAGE-67-TS-10 systems following the master/slave principle ....31 Shutdown .
Page 4
10.2 Capacity expansion using additional STORAGE-67-TS-10 units........
(STPS 60-10) manufactured by SMA. Any other use must be approved by the manufacturer and, if necessary, the local utility company. The unit may be operated only in closed rooms. The STORAGE-67-TS-10 works in an ambient air temperature range of -10 ° C to 50 ° C and at a maximum humidity of 85 %.
8 SAFETy 2 Safety The STORAGE-67-TS-10 meets the requirements of IEC 61508 parts 1 to 7 and complies with safety integrity level (SIL) 1. DANGER! Life-threatening electric shock from damaged components or short circuit Bridging the battery poles causes a short circuit resulting in a flow of electrical current. A short circuit of this type must be avoided under all circumstances.
The use of a hand truck is recommended. Caution: Do not damage the casing! The individual components of the STORAGE-67-TS-10 can weigh up to 120 kg and are therefore should not be transported by a single person. It is recommended that the system be installed by at least two people. The assis- tance of a hand truck is helpful.
The STORAGE-67-TS-10 has been optimized for use with the 3-phase STPS 60-10 battery inverter. The overall system is perfectly matched to the needs of trade and industry. Thanks to the SMA Inverter Manager’s flexible energy management system and its high C-rate, STORAGE-67-TS-10 storage systems can be used for an extremely wide variety of applications.
18 APU Fuse (F1) Fuse element to protect the SMA HV APU (2 A time-delay fuse (T) 5 x 20 mm, in accordance with DIN 41571- 2 type 521.020 from ESKA, 250 V ). System cannot be operated with a defective fuse.
7 .5 cabinet. NOTE Before installing the SMA HV APU, note its serial number. This is located on a sticker on the underside of the cabinet. Grounding the SMA HV APU is absolutely essential. Connect the...
The e-stop is used to quickly shut down the system. Since the battery storage system is not switched off properly when the e-stop is used, damage may be caused to components of the STORAGE-67-TS-10. you must therefore never use the e-stop to switch off the unit under normal circumstances.
Always follow the specifications for connecting the STORAGE-67-TS-10 and the STPS 60-10. For example, no additional consumers or components may be included in the DC intermediate circuit between the battery and inverter. you must always consult the SMA Service center about any changes you would like to make to the sys- tem setup.
The STPS 60-10 has been installed in accordance with the installation and connection specifications. Procedure Check the cabling of the STPS 60-10 and the STORAGE-67-TS-10 (also see the STPS 60-10 installation guide). Check the cabling of the components in accordance with section ““5.5 Battery module wiring“ on page 17 et seq.
The STPS 60-10 has been installed in accordance with the installation and connection specifications. Procedure Check the cabling of the STPS 60-10 and the STORAGE-67-TS-10 (see the STPS 60-10 installation guide). Check the cabling of the components in accordance with section “5.5 Battery module wiring“ on page 17 et seq.
Press the “Plant Stop” button at the top right of the LCS tool. The Inverter Manager will then lower the power out- put of the STPS to 0 kW, open the AC contactor of the STPS and give the command to the SMA HV APU to dis- connect from the DC path.
. In the event of any discrepancies, please contact our service center. Adjust the voltage of the original battery modules of the STORAGE-67-TS-10 so that it matches the voltage of the new battery modules exactly. Use the LCS tool. Further information on the procedure can be found in the follow- ing section “Adjusting the battery voltage via the LCS tool“...
Adjusting the battery voltage via the LCS tool NOTE For authoritative instructions on the LCS tool, please consult the applicable product documentation. Enter your SMA Grid Guard Code in the “Service” > “Grid Guard” tab. If you do not have the code, please contact our service center.
40 EXPANSION OF THE STORAGE SySTEM Overview of all addressing options BATTERY CHARGER ADDRESS Set the address selector on the SMA High-Voltage Active Power Unit (SMA HV APU) to match the configuration and information in the table below. LEFT SWITCH RIGHT SWITCH DESIGNATION...
The “System” menu item at the bottom of the BatMon interface includes a “Communication Port” button. Here, the serial number of the SMA HV APU must be selected under “Select APU” (this serial number can be found on a sticker on the underside of the SMA HV APU casing).
This value indicates the percentage to which the battery has been charged. 100 % means that the battery is fully charged. The SMA HV APU can use the parameters to determine the state of charge of a cell or battery module, and to stop the charging process if necessary, thereby preventing overcharging.
STOP STOP Before carrying out maintenance work, ensure that the STORAGE-67-TS-10 is taken out of operation in accor- dance with the instructions in section “9 Shutdown“ on page 34. NOTE: When cleaning and maintaining the STPS 60-10, always follow the specifications and instructions in the technical documentation for the STPS 60-10.