The next step is to connect the flown array to additional B28 stacks on the ground. Lift the flown array high enough to allow a stack to
be placed under the array. Once aligned, lower the flown array onto the stack. The two skids under the B28 will align the arrays. If the
cabinets are not perfectly aligned, gently push the flown array for alignment. Once the arrays are stacked, deploy the rigging and secure
the cabinets together. There is no need to deploy the link bars ahead of time.
STEPS:
Lower the flown array onto the next B28 stack.
1
2
Open the LOCK (if not open already).
3
Extend the link bar.
4
Close the LOCK.
Repeat the steps until the entire array is assembled.