Checking The Function Of The Ups - SMA SUNNY CENTRAL 500CP-JP Maintenance Manual

Hide thumbs Also See for SUNNY CENTRAL 500CP-JP:
Table of Contents

Advertisement

SMA Solar Technology AG
4. Check whether the heating elements are radiating heat after a delay time of five minutes.
If the heating elements are not radiating heat, contact us (see Section 9 "Contact", page 67).
5. Reset the hygrostat to the initial value. To do this, press the selector switch back towards the hygrostat. The initial
value of the hygrostat is indicated on the hygrostat.
6.4.1.5

Checking the Function of the UPS

Figure 14: Positon of the UPS
Position
Designation
A
Uninterruptible power supply (UPS)
Danger to life due to electric shock or electric arc if live components are touched
• Switch off the inverter and wait at least 15 minutes before opening it to allow the capacitors to discharge
completely.
• Disconnect the inverter (see Section 4, page 25).
Procedure:
1. Switch the inverter to Stop.
2. Connect the supply voltage (see Section 4.3.1, page 27).
3. Measure the voltage at the supply voltage output between L1 and N.
☑ The voltage is approximately 230 V.
✖ Voltage deviates significantly?
• Contact Service.