Commissioning; Commissioning Tasks - Beko CLEARPOINT 3eco S040 Installation And Operation Manual

Coalescing filter
Table of Contents

Advertisement

Installation and operation manual

8. Commissioning

8.1 Commissioning tasks

For commissioning to be carried out, the following prerequisites must be fulfilled and the preparatory tasks must have 
been completed.
Tools
none
1.
Assembly finished including subsequent leakage test
Automatic discharge
none
Preparation of installation
Figure
Mechanically open
Figure
1
3
2
Prerequisites
Material
Description
1. Set the knurled screw on the float 
drain from >>Mechanically open<<
anti-clockwise (left-hand thread) to
>>Automatic discharge<<
Description
2. Open the shut-off valve [1] on the inlet
side slowly
3. Open the shut-off valve [2] on the outlet
side slowly
4. Close the shut-off valve [3] of the bypass
pipe
CLEARPOINT
3eco
coalescing filter
®
Protective equipment
None