b.
Rotate the CMA out of the way to gain access to the power supply bay.
Step 3.
If there is a power-supply filler installed, remove it.
Figure 26. Hot-swap power supply filler removal
Step 4.
Slide the new hot-swap power supply into the bay until it snaps into position.
Figure 27. Hot-swap power supply installation
After installing the power supply:
1. Connect one end of the power cord to the new power supply connector; then, connect the other end of
the power cord into a properly grounded electrical outlet.
2. If the server is powered off, power on the server. Ensure that the power supply is replaced successfully:
• The amber warning LED on node front panel is off.
• The green indicator light on each power supply is illuminated.
• No errors are shown in the Lenovo XClarity Controller.
64
User Guide for ThinkAgile VX2320, VX3320